1
Make Ready Engineering
Examine existing infrastructure, and create design sheets.
Timeline: About 18 weeks
Make Ready Construction
Upgrade existing infrastructure to make it ready for addition of fiber lines.
Timeline: About 18 weeks
2
3
Construction
Bury fiber cable underground and string it from poles to build the network that connects homes and business to our fiber network.
Timeline: About 14 weeks
Splicing
Splice the necessary cables at each end point and mount splices in enclosures secured to distribution poles.
Timeline: About 14 weeks
4
5
Service Drop
Extend the fiber cable from the nearest splice point to the area receiving service.
Timeline: About 6 weeks
Drop Splicing
This final outdoor step in a fiber construction project gets the network ready to be connected to homes and businesses.
Timeline: About 6 weeks
6
7
Installation
Once the fiber network is ready, the team will hook up homes and businesses to receive reliable, highspeed internet service.
Timeline: About 6 weeks